Jilin Petrochemical’s 240,000‑ton‑per‑year bisphenol A unit achieved successful single‑run commissioning.

Share:

At 10:28 on May 16, 2026, with the smooth packaging of the first batch of bisphenol A qualified products, Jilin Petrochemical Company's 240000-ton/year bisphenol A plant was successfully started.

The device introduces Begier's ion exchange resin process and adopts two-stage adduct crystallization treatment methodology, with a product purity of 99.95, meeting the needs of all downstream consumers, including optical grade polycarbonate manufacturers, to high-condition raw materials. The construction of the project started on June 9, 2023 and lasted nearly two years. A total of 22403 cubic meters of concrete was poured, 4653 tons of steel structure was installed, and 3080 sets of electrical, instrument and equipment were installed. The project was successfully handed over on April 30, 2025.

As the first bisphenol A plant of PetroChina, the project has been completed and put into operation to fill the gap of the group company in the field of this product. It is of great significance to Jilin Petrochemical Company to further extend the manufacturing chain of "propylene-phenol/acetone-bisphenol A" and accelerate the transformation from "oil refining to chemical sector, chemical sector to materials, and materials to medium and high end". It will play a key role in promoting and perfecting the layout of the whole manufacturing chain of "refining refined materials.

There is no mature start-up precedent and no ready-made operation experience to reference in CNPC. Phenol raw materials and bisphenol A items have high freezing point characteristics, the system temperature manage, pipeline heat tracing, material transportation conditions are extremely demanding. In the face of difficulties and challenges, the company and the factory have set up special work classes to complete the preparation of the test run plan, personnel training and multiple rounds of desktop deduction with high condition. They adhere to the daily regular meeting system. Cadres sink to the front line and command in the whole process. All managers, technical backbones and post operation backbones are stationed 24 hours a day, keeping a close eye on every link, every group of parameters and every node in the operation of the device.

In the process of driving, strictly implement the principle of "people follow materials", strictly implement the security risk classification manage and hidden danger investigation and regulation mechanism, and strictly implement the work permit, process discipline and operation standards. Implement grid regulation and manage, practice instead of war, practice to promote learning, and comprehensively enhance the technical level and practical operation ability of all staff. The staff is equipped with the "five-piece set" of inspection, carefully monitoring the plate, fine inspection and accurate operation, refining the special manage measures to anti-freezing, anti-condensation, anti-crystallization and anti-clogging of high condensation point materials, accurately adjusting the temperature, pressure, flow rate and material ratio, repeatedly optimizing the process operation parameters, and solving a series of technical problems such as high condensation point material manage one by one.

Relying on cutting-edge methodology and precise manage of the whole process, the 240000-ton/year bisphenol A plant took only 4 days from 9: 00 on might 12 to create qualified items.