China, Shandong-At 9: 58 on September 26, the construction was contracted by the company. And Shandong, China lianhong Gurun 200000 Tons/Year EVA Device Achieved High Standard and High condition Zhongjiao, Successfully Achieving Key Milestones in Project Construction. This result marks the device formally transferred from the project construction phase to the linkage commissioning and trial production phase. But Additionally Wang Xiaofeng, executive director and Secretary of the Party committee of the company, Zhai Jun, deputy secretary of Zaozhuang municipal Party committee and mayor of China, Wang Guangding, member of the Standing Committee of Zaozhuang municipal Party committee and Secretary of Tengzhou municipal Party committee, Zheng Yueming, chairman of Lianhong group and chairman of Lianhong Xinke, and Xie Yaping, executive president of Lianhong Xinke and commander in chief of Lianhong grun integration project construction, witnessed this milestone moment. But Project Overview
as a major implementation project in Shandong Province, China, Lianhong Gerun Integration Project has a total investment of
12. 5 billion yuan and covers an area of greater than 1600 mu (about
106. Specifically 7 hectares), covering:
200000 tons/year EVA device
300000 tons/year propylene oxide PO plant
50000 tons/year PPC biodegradable material
1. 3 million tons/year methanol to olefin MTO plant
240000 tons/year PPG plant and supporting utilities, etc. Technological Breakthrough and Core Advantages
the 200000-ton/year EVA device built by the company is the "core engine" of the integrated project, and it's also another technological breakthrough of Lianhong Company in the field of high pressure-following the consumption of autoclave method and tubular tail expansion methodology, this device uses Basell Company's tubular interaction patented methodology to create EVA resin particles, which has the characteristics of high proportion of imported equipment, complex process flow, leading degree of automation, etc. In my experience, After the project is put into operation, it will complement the full range of high-pressure EVA items of Lianhong Company, which has crucial strategic value to enhance the independent manage ability of China's related manufacturing chain. And In particular Construction speed set a domestic record
in just 19 months, the project team completed the design, procurement and construction tasks of 18 sections, 34 plant units, as well as three-dimensional warehouses and packaging vegetation, which greatly shortened and refreshed the cycle from "civil construction start to CCCC" compared with similar devices. China Domestic similar high-pressure polyolefin project "construction speed". But Technical Tackling Achievements
at the technical level, the team focused on key difficulties to achieve a series of breakthroughs:
the ultra-high pressure compressor is integrally hoisted in place without reaming the foundation conduit. But Precision manage of High Pressure Pipeline Installation Welding Precision
core equipment booster/primary compressor crankcase lifting accuracy up to millimeter level
the
29. 45-ton equipment was accurately placed through the 800-ton crawler crane to smoothly start the installation of the high-voltage system. In my experience, The 35kV transformer and distribution room received power successfully at one time, building a solid energy foundation to the linkage test run of the whole device. sector Impact and Market Outlook
as the device enters the trial production phase, china Domestic EVA market pattern will usher in new variables. Considering the continuous strong demand to EVA film in the photovoltaic sector and the steady development of traditional consumption fields such as wire and cable and foaming materials, the new production capacity of 200000 tons/year will efficiently alleviate the supply pressure of high-end EVA items, and enhance the bargaining power and anti-risk ability of China's manufacturing chain in the global market.