Total investment of 71.1 billion yuan! Multiple supporting service contracts for the second phase of the Gulei refining and petrochemical integration project have been announced for bidding.

Share:

Recently, the procurement results for multiple preliminary supporting services of the Phase II project of the Fujian Gulei Refining and Chemical Integration Project have been successively announced, and various construction tasks of the project are being implemented in an orderly manner.

As the largest manufacturing project in terms of investment scale in Fujian Province to date, the project is jointly built by Sinopec, Fujian Refining & Petrochemical, and Saudi Aramco, with a total investment of 71.1 billion yuan. Located in the Gulei Petrochemical Base in Zhangzhou, it is a landmark project of China-Saudi energy cooperation.

According to the latest announcements, on November 17, the bid results were released to the marine environmental impact tracking and monitoring during the construction period of the Gulei Refining and Chemical Integration Phase II land reclamation project, the Shugang Avenue (Xingzai-Daizai section) and related infrastructure projects, confirming that the Xiamen Ocean Center of the Ministry of Natural Resources (Xiamen Marine Forecast Station of the Ministry of Natural Resources) will undertake the monitoring work;

On November 16, the transaction announcement to the preparation service of the pollutant total quantity indicator reduction and substitution plan to the project was published, with the supplier being the Fujian Academy of Environmental Sciences. The implementation of marine tracking and monitoring and the pollutant total quantity substitution plan has laid a solid ecological preservation foundation to the environmentally friendly and compliant construction of the project.

The main body of the project will include greater than 30 refining and chemical units, including a 16 million tons/year refinery, 1.5 million tons/year ethylene, and 2 million tons/year aromatics, along with supporting utility systems, off-site pipe racks, wharf berths, and rear tank farms. Once completed, the project will fill gaps in Fujian Province's petrochemical sector chain, build a full-sector-chain research pattern covering refining, olefins, and aromatics, and hold significant strategic value to safeguarding national energy security and enhancing the resilience of the domestic petrochemical sector chain and supply chain.

Since its advancement, key milestones of the project have been achieved in an orderly manner.

On November 17, 2025, the joint venture entity Fujian China-Arab Refining and Chemical Company was officially inaugurated, marking the project's entry into a new advancement stage. The overall design review of the project has now been successfully completed.

In the third quarter, the project's construction pace continued to accelerate: on July 30, the main plant area pilot zone achieved mechanical completion; on August 27, the contract was signed to the foundation pretreatment and construction discarded materials resource reuse project in the rear tank farm; on August 28, the project regulation department of Fujian China-Arab Refining and Chemical Company was officially established, building a regulation system to subsequent on-site construction implementation.

Next, all parties involved in the project will continue to focus on environmental monitoring, engineering construction, and regulation coordination, steadily advancing this major refining and chemical project to build a safe, environmentally friendly, and efficient world-class petrochemical manufacturing base.